J16/J16A Online Exhibition (Penmaenmawr & Dwygyfylchi)

Find out about the proposed scheme for A55 Junctions 16 and 16A.

The Proposed Scheme

The Scheme proposes to remove the roundabout at Junction 16, near to Penamaenmawr and Dwygyfylchi, replacing it with a grade-separated junction at Junction 16A and a new link road connection to Junction 16 where the westbound slip roads would be retained.

The proposed scheme comprises of:

Landscape, townscape design features and environmental mitigation comprises of:

Visualisation of Scheme looking east across new Junction 16 towards Dwygyfylchi and Penmaenbach headland

Visualisation of Scheme looking east across new Junction 16 towards Dwygyfylchi and Penmaenbach headland

Visualisation of Scheme looking west across new height separated Junction 16A and overbridge and link road towards Penmaenmawr.

Visualisation of Scheme looking west across new height separated Junction 16A and overbridge and link road towards Penmaenmawr.

You can find out more about the proposals by reading the Scheme Assessment Report and the Environmental Statement Non-Technical Summary, which can be found in the project Document library, or by exploring the Scheme Layout Plan and Environmental Master Plans (EMP). You can also see what the scheme might look like after construction by watching the fly-through.

warning_icon
This video requires cookies to be enabled. You can change your cookie settings or watch this video on YouTube. Note that watching on YouTube may store cookies on your device.

Proposed Scheme Active Travel and NMU Improvements

The scheme proposals incorporate Active Travel and Non-Motorised Improvements which start on the eastern edge of Penmaenmawr and run along Conway Road to Junction 16. The improvements then extend along the length of the proposed link road to the northern side of Dwygyfylchi at J16A and connect into National Cycle Route NCNR5 and Dwygyfylchi at the eastern end.

Features include:

Visualisation of the shared cycle/footway and pedestrian crossing at the Penmaenamawr Phoenix football club, looking eastwards along Conway Road towards Junction 16.

Visualisation of the shared cycle/footway and pedestrian crossing across the link road, from Maes Y Llan to the replacement Puffin footbridge.

Visualisation of the shared cycle/footway and cattle grid bypass, looking northwards along the widened Glan-Yr-Afon Road towards Junction 16A.

Interactive scheme map

You can use the maps below to zoom in and explore the scheme. If you are unable to view the maps, copies of the proposed scheme plans can be found in the PDF of the exhibition in the Document library.

warning_icon
The interactive maps require cookies to be enabled. You can change your cookie settings.
Junction 16/16A – Proposed Scheme Layout Plan 1 of 3 (Penmaenmawr and Dwygyfylchi)

Junction 16/16A – Proposed Scheme Layout Plan 1 of 3 (Penmaenmawr and Dwygyfylchi)


Junction 16/16A – Proposed Scheme Layout Plan 2 of 3 (Penmaenmawr and Dwygyfylchi)

Junction 16/16A – Proposed Scheme Layout Plan 2 of 3 (Penmaenmawr and Dwygyfylchi)


Junction 16/16A – Proposed Scheme Layout Plan 3 of 3 (Penmaenmawr and Dwygyfylchi)

Junction 16/16A – Proposed Scheme Layout Plan 3 of 3 (Penmaenmawr and Dwygyfylchi)


Plan Key Details
1. Furthest extent of footway/cycleway (NMU) improvements.
2. Shared footway/cycleway from the edge of Penmaenmawr along Conway Road to Junction 16.
3. Existing road crossing retained at Penmaenmawr Football Club.
4. Extent of proposed works to tie-in with existing A55 Trunk Road at Junction 16.
5. Proposed roundabout.
6. Location of existing roundabout (to be removed).
7. Westbound slip roads.
8. Improvements to the existing National Cycle Network Route 5 (NCNR5) and Wales Coast Path for a length to the north of Junction 16.
9. Proposed priority junction with Ysgurborwen Road.
10. Relocated bus stop.
11. Environmental mitigation area to encourage reptiles.
12. Planted earthwork bank, or false cutting, to screen views of the link road and A55 Trunk Road from the south.
13. Proposed link road with a shared footway/cycleway along the southern side.
14. Proposed ramp from Maes-Y-Llan to tie in with the new footway/cycleway along the south side of the link road.
15. Relocated playing field.
16. Proposed link road crossing to the replacement Puffin footbridge and services, ties in with the locally realigned Public Footpath Penmaenmawr 8.
17. Replacement footbridge with diabilty compliant ramps to provide access to the NCNR5 and the beach.
18. New public open space to mitigate loss of amenity area.
19. Fenced area with stormwater attenuation pond and other link road infrastructure.
20. Trees and shrubs to screen views of the link road and A55 Trunk Road from the south.
21. Existing footpath (formerly Old Bangor Fields Road) to tie in with new shared foot/cycleway along south side of link road.
22. Proposed Glan-yr-Afon Road widening and shared foot/cycleway on western side of road, ties in with the existing footpath (formerly Old Bangor Fields Road).
23. Furthest extent of improvements on Glan-yr-Afon Road.
24. Relocated cattle grid with a gated bypass for non-vehicular users. Bus stop to be relocated.
25. Maintenance layby.
26. Proposed link road crossing at Glan-yr-Afon Road to provide access to foot/cycleway route to the NCNR5 and beach using the new bridge over the A55 Trunk Road.
27. Link road rises on raised embankments as it approaches the new overbridge at Junction 16A. Planting of trees and shrubs around the junction screens views to the south.
28. Proposed crossing of the westbound on slip road for non-vehicular users.
29. Proposed overbridge at Junction 16A.
30. Relocated access to the DCWW sewage treatment works.
31. Proposed crossing of the eastbound off slip road for non-vehicular users.
32. Existing National Cycle Network Route 5 (NCNR5) and Wales Coast Path realigned at Junction 16A to accommodate new slip roads.
33. Access to maintenance layby from sliproad.
34. Culverted watercourse.
35. Extent of proposed works to tie-in with existing A55 Trunk Road at Junction 16A.

The Draft Orders

Copies of the plans for the draft Chester to Bangor Trunk Road (A55) Junctions 16 and 16A Improvement Realignment and Slip Roads Order, accompanying draft Side Road Order and draft Compulsory Purchase Order (CPO) can be found below. To see a larger image, please click its thumbnail picture.

The draft Orders, schedules, tables that accompany these plans can be found on the project website. Hard copies can be viewed by appointment at a deposit location. Any person or organisation can object, make representations, support, suggest or comment on the published draft Orders. You can find out how to send us your response on the Submit Your Views page.

Junctions 16 and 16A draft Realignment and Slip Roads, Side Roads Order:

Your response, for the draft Chester to Bangor Trunk Road (A55) Junctions 16 and 16A Improvement Realignment and Slip Roads Order, and accompanying draft Side Road Order, should be sent to arrive at the Welsh Government no later than 7 May 2021, quoting reference qA1420023 and stating the grounds of objection.

Site Plan A (Junction 16)

Site Plan A (Junction 16)


Site Plan B (Junction 16)

Site Plan B (Junction 16)


Site Plan 1

Site Plan 1


Site Plan 2

Site Plan 2


Site Plan 3

Site Plan 3


Site Plan 4

Site Plan 4


Junctions 16 and 16A draft Compulsory Purchase Order:

Your response, for the draft Chester to Bangor Trunk Road (A55) Junctions 16 and 16A Improvement Realignment and Slip Roads Compulsory Purchase Order (CPO), should be sent to arrive at the Welsh Government no later than 7 May 2021, quoting reference qA1420042 and stating the grounds of objection.

Junctions 16 and 16A Draft Compulsory Purchase Order Sheet 1 of 4

Junctions 16 and 16A Draft Compulsory Purchase Order Sheet 1 of 4


Junctions 16 and 16A Draft Compulsory Purchase Order Sheet 2 of 4

Junctions 16 and 16A Draft Compulsory Purchase Order Sheet 2 of 4


Junctions 16 and 16A Draft Compulsory Purchase Order Sheet 3 of 4

Junctions 16 and 16A Draft Compulsory Purchase Order Sheet 3 of 4


Junctions 16 and 16A Draft Compulsory Purchase Order Sheet 4 of 4

Junctions 16 and 16A Draft Compulsory Purchase Order Sheet 4 of 4


Section 19 Certificate Map Public Open Space Land Take and Exchange Land Sheet 1 of 2

Section 19 Certificate Map Public Open Space Land Take and Exchange Land Sheet 1 of 2


Section 19 Certificate Map Public Open Space Land Take and Exchange Land Sheet 2 of 2

Section 19 Certificate Map Public Open Space Land Take and Exchange Land Sheet 2 of 2


The Environmental Master Plan

The Environmental Master Plans (EMP) illustrate the environmental mitigation measures incorporated within the design of the Scheme, including details of the proposed landscape work. Further information can be found in the Environmental Statement or the Non-Technical Statement (NTS), in the Document library.

To see a larger image of the Environmental Master Plans below, please click its thumbnail picture.

Environmental Master Plan Sheet 1 of 3 (Penmaenmawr & Dwygyfylchi)

Environmental Master Plan Sheet 1 of 3 (Penmaenmawr & Dwygyfylchi)


Environmental Master Plan Sheet 2 of 3 (Penmaenmawr & Dwygyfylchi)

Environmental Master Plan Sheet 2 of 3 (Penmaenmawr & Dwygyfylchi)


Environmental Master Plan Sheet 3 of 3 (Penmaenmawr & Dwygyfylchi)

Environmental Master Plan Sheet 3 of 3 (Penmaenmawr & Dwygyfylchi)


Junction 16/16A Next Steps

Winter 2020/2021 Publication of draft Orders and the Environmental Statement

These will set out the land that would be required to build the Scheme and the environmental mitigation work that would be involved. It would detail local accesses and provision of Private Means of Access. You will then have the opportunity to formally object or support the Scheme or suggest an alternative.

Summer 2021 Potential Public Inquiry

If a Public Inquiry is required, an independent Inspector would hear evidence, in front of the public, from interested parties and stakeholders. The Inspector would make a recommendation to the Welsh Ministers on how to proceed.

Autumn 2021 Welsh Ministers decision to make the Orders

The Welsh Ministers would decide whether to make Orders and to go ahead with the construction of the project.

Autumn 2021 Appoint Design & Build (D&B) contractor subject to Welsh Ministers decision

Subject to the decision to proceed with the Scheme, the Contractor who will undertake the detailed design and build would be appointed by the Welsh Government.

Winter 2021/2022 Commence construction on site

Works to build the new junction 16 and other associated improvements would start.

Autumn 2023 junction 16 improvements open

The completed junction 16 improvement scheme at Penmaenmawr and Dwygyfylchi would open.